ERIN – A Wellington County committee is set to receive an update on the new Erin Library construction project.
The new library will be located at the former grist mill in the Village of Erin.
A report going before the Information, Heritage, and Seniors Committee on Wednesday afternoon lays out where the project is now.
Work completed to date includes:
- Mechanical & electrical trades have completed installing their underground services
- Installation of rebar for concrete grade beams has been completed
- Below slab vapor barrier has been installed
- Concrete floor slab has been poured
- Masons have begun repairs to existing structure
- Masons have started the block walls for the elevator shaft
Work to be completed in the next month includes:
- Masons will continue repairs to existing structure (Int. & Ext.)
- Masons continue installation of block walls for the elevator shaft
- Structural steel installation is scheduled to begin
The $12.8 million project is scheduled to be completed in the spring of 2025.
You can find Wednesday’s report here.